When to Remove Concrete Forms?

Published in Concrete Form Removal 3 mins read

Concrete forms can typically be removed 24-48 hours after pouring and finishing the slab, provided the concrete has gained sufficient strength.

Understanding Concrete Strength and Form Removal

Removing concrete forms, or formwork, too early can compromise the structural integrity of the concrete element. The critical factor is not just time, but the concrete's compressive strength.

According to construction practices, after pouring and finishing, you should generally wait 24-48 hours before removing concrete forms. This waiting period allows the concrete to gain enough initial strength to support itself without cracking or deforming.

Signs and Conditions for Removal

  • Time Elapsed: Wait the recommended 24-48 hours after pouring and finishing the slab.
  • Sufficient Strength: The concrete must have developed enough strength to stand on its own without crumbling or cracking at the edges when forms are gently pried away.
  • Natural Contraction: As concrete cures, it naturally contracts slightly. This contraction causes it to pull away from the forms, which makes them easier to remove.

Factors Influencing Removal Time

While 24-48 hours is a general guideline for slabs, the exact time can vary depending on several factors:

  • Concrete Mix Design: Different mixes cure at different rates. High-early-strength concrete gains strength faster.
  • Temperature: Concrete cures slower in cold weather and faster in hot weather. Very low temperatures can halt curing.
  • Humidity: Proper moisture is essential for curing. Dry conditions can slow strength gain.
  • Size and Type of Element: While the 24-48 hour rule often applies to non-load-bearing slabs and walls, structural elements like beams, columns, or suspended slabs require longer periods to achieve adequate strength before forms can be removed, sometimes days or even weeks. Note: The provided reference specifically mentions removing forms for a "slab" within 24-48 hours.
  • Admixtures Used: Certain admixtures can accelerate or retard setting and curing times.

Best Practices for Form Removal

  • Always check local building codes and project specifications, as they may require specific strength tests before form removal.
  • Remove fasteners carefully.
  • Gently pry the forms away from the concrete. Avoid using excessive force that could damage the edges or surface.
  • Once forms are removed, continue proper curing (like applying curing compounds or keeping the concrete moist) to ensure the concrete reaches its full design strength.

Knowing when to remove forms is a balance between allowing sufficient curing time for strength gain and keeping the project on schedule. The 24-48 hour timeframe for slabs, combined with verifying the concrete's strength and observing its natural contraction from the forms, provides a reliable indicator.