What is CPI PMP?

Published in Project Cost Management 3 mins read

In project management, particularly within the context of the PMP® certification and Earned Value Management (EVM), CPI stands for Cost Performance Index. It is a key metric used to measure the cost efficiency of a project.

Understanding CPI in Project Management

The Cost Performance Index (CPI) provides a crucial indicator of how well a project is managing its budget against the work completed. It's a fundamental tool for monitoring and controlling project costs.

CPI Definition and Calculation

The CPI is calculated using two core values from Earned Value Management:

  • Earned Value (EV): The value of the work performed to date.
  • Actual Cost (AC): The total cost incurred for the work performed to date.

According to project management principles, to calculate CPI:

  • To calculate CPI, you divide the project's Earned Value by its Actual Cost.

This is represented by the formula:

CPI = Earned Value (EV) / Actual Cost (AC)

Interpreting the CPI Value

The resulting CPI figure provides immediate insight into the project's cost performance relative to the plan. Based on the calculation:

  • A CPI greater than 1 indicates you're under budget.
  • A CPI of 1 means you're on budget.
  • A CPI less than 1 suggests you're over budget.

You can visualize the interpretation like this:

CPI Value Interpretation Cost Efficiency
CPI > 1 Under Budget Efficient (Spending Less for Work Done)
CPI = 1 On Budget As Planned
CPI < 1 Over Budget Inefficient (Spending More for Work Done)

A CPI of less than 1 is a warning sign that the project is costing more than planned for the work accomplished and requires attention to bring costs back under control.

Why CPI Matters

Tracking CPI is vital for project managers as it helps in:

  • Performance Monitoring: Provides a clear, objective view of cost performance at any point in time.
  • Forecasting: Used in conjunction with other EVM metrics (like SPI - Schedule Performance Index) to forecast the final cost of the project (Estimate at Completion - EAC).
  • Decision Making: Helps identify cost issues early, allowing for corrective actions to be taken before they significantly impact the project's success.

Understanding and utilizing the CPI is a critical skill for project managers, essential for passing the PMP exam and successfully managing project finances in practice.