askvity

How to Calculate Total Float

Published in Project Management 3 mins read

Calculating total float is a fundamental step in project scheduling to understand the flexibility of tasks within a project timeline. Total float represents the amount of time a task can be delayed without impacting the project's overall completion date or violating any schedule constraints.

Understanding Total Float

Total float helps project managers identify which activities are critical (having zero or negative float) and which have buffer time. This knowledge is crucial for resource allocation, risk management, and schedule adjustments.

Methods for Calculating Total Float

According to project scheduling principles, you can calculate total float using the task's early and late dates. The reference provided gives two equivalent methods:

  1. Using Latest Finish (LF) and Earliest Finish (EF) Dates:
    To calculate total float, subtract the task's earliest finish (EF) date from its latest finish (LF) date.

    • Formula: LF - EF = total float
  2. Using Latest Start (LS) and Earliest Start (ES) Dates:
    Alternately, you can subtract the task's earliest start (ES) date from its latest start (LS) date.

    • Formula: LS - ES = total float

Both formulas yield the same result for any given task in a project schedule.

Key Terms:

  • Earliest Start (ES): The earliest possible time an activity can start, based on the project network logic and any schedule constraints.
  • Earliest Finish (EF): The earliest possible time an activity can finish, calculated as ES + duration.
  • Latest Finish (LF): The latest possible time an activity can finish without delaying the project finish date or violating a schedule constraint.
  • Latest Start (LS): The latest possible time an activity can start without delaying the project finish date or violating a schedule constraint, calculated as LF - duration.

Example Calculation

Let's illustrate with a simple example for a hypothetical Task A:

Suppose Task A has the following dates:

  • Earliest Start (ES): Day 5
  • Earliest Finish (EF): Day 10 (assuming a 5-day duration)
  • Latest Start (LS): Day 8
  • Latest Finish (LF): Day 13

Using the first method (LF - EF):
Total Float = LF - EF = 13 - 10 = 3 days

Using the second method (LS - ES):
Total Float = LS - ES = 8 - 5 = 3 days

In this example, Task A has 3 days of total float. This means Task A can be delayed by up to 3 days from its earliest dates without affecting the project's overall completion date.

Importance of Total Float

Knowing the total float for each task helps in:

  • Identifying the Critical Path: Tasks with zero or negative total float are on the critical path, meaning any delay in these tasks will delay the entire project.
  • Prioritizing Work: Tasks with less float require closer monitoring.
  • Resource Leveling: Resources can potentially be shifted from tasks with high float to tasks on the critical path.
  • Managing Risk: Understanding float helps assess the impact of potential delays.

By calculating total float using either the LF - EF or LS - ES formula, project managers gain valuable insight into schedule flexibility and critical activities.

Related Articles